How to Create a Project Plan Using PRINCE2
To learn how to create a project plan using PRINCE2, start by defining what your project needs to deliver, rather than immediately listing tasks or creating a schedule.
PRINCE2® uses a product-focused planning technique that begins with the required products and develops the work packages, estimates, schedule, budget, and controls needed to deliver them.
The PRINCE2 planning technique involves:
- Define and analyse products: Establish what needs to be delivered, how products relate, and how their quality will be assessed.
- Organise Work Packages: Group the work required to produce and deliver those products.
- Prepare estimates: Work out the people, resources, time, costs, and other estimates needed.
- Prepare the schedule: Identify when the work can realistically be completed.
- Prepare the budget: Calculate the expected costs of delivery and management.
- Analyse risks: Identify uncertainties and adjust the Plan where necessary.
- Document the Plan: Bring together the information needed for review, approval, and ongoing control.
These activities are not completely sequential. For example, preparing estimates may reveal scheduling constraints, while identifying risks may require changes to the proposed work.
Want to apply these steps to your own project? Our free PRINCE2 Project Planning Toolkit includes editable Word and Excel templates to help you organise products, Work Packages, estimates, schedules, risks, and project controls. Download both resources and adapt them to your own project.
What Is the PRINCE2 Plans Practice?
The PRINCE2 Plans Practice explains how a project defines and organises the products, people, resources, activities, and timing needed to achieve its objectives.
It addresses three fundamental questions: How? How much? When?
A Plan connects what users expect to receive with how the project team proposes to deliver it and the resources the organisation is prepared to commit.
This helps decision-makers determine whether the proposed work is realistic, affordable, and aligned with the Business Case.
The Plans Practice also supports control. Once a Plan is approved, the project management team can compare actual and forecast progress against the agreed targets.
Planning is therefore not something that happens only at the beginning of a project. Plans are reviewed and updated appropriately as the project progresses.
For an overview of how planning connects with the other practices, read our guide to the seven PRINCE2 Practices.
What Is a PRINCE2 Project Plan?
A PRINCE2 Project Plan describes how the project intends to achieve its objectives across the project lifecycle. It identifies the major products, activities, resources, and people required, and provides a basis for monitoring overall progress.
Think of the Project Plan as the overall delivery picture.
A schedule might tell you that a new software system should be ready for testing in September.
The Project Plan should provide the wider information needed to understand what must be delivered, the work involved, the expected costs, the dependencies, and how progress will be controlled.
A Project Plan may include:
- The scope of the project.
- Products to be delivered.
- Dependencies, assumptions, and prerequisites.
- Relevant lessons from previous work.
- Work Packages and delivery activities.
- Budgets and schedules.
- Performance targets and tolerances.
- Monitoring, control, and reporting arrangements.
It doesn’t necessarily mean creating one enormous document. PRINCE2 allows planning information to be maintained in different documents, systems, and formats.
The important point is that the information is available, understood, and suitable for managing the project.
For more information about how Plans fit alongside other project documents and records, explore our PRINCE2 Management Products guide.
What Types of Plan Does PRINCE2 Use?
PRINCE2 identifies four types of Plan: Project Plans, Stage Plans, Team Plans, and Exception Plans.
They have different purposes and levels of detail, allowing planning and control to take place at appropriate management levels.
| Plan | What it covers | Key point |
|---|---|---|
| Project Plan | The overall project | Provides project-level direction and control |
| Stage Plan | A particular management stage | Supports detailed stage management |
| Team Plan | Work undertaken by a delivery team | Optional, depending on the project |
| Exception Plan | Directed actions in response to an exception | Used when required following an Exception Report |
Project Plan
The Project Plan covers the overall project lifecycle and is prepared during the Initiating a Project process.
It provides a higher-level view of the project’s stages, major products, resources, and expected performance.
Once approved, it becomes an important baseline for monitoring progress and assessing changes.
Stage Plan
A Stage Plan focuses on one management stage and provides the detail required for the Project Manager to control that stage.
Because it covers a shorter period, it can usually contain more reliable estimates and more detailed delivery activities than the overall Project Plan.
For example, a Project Plan may show that a software implementation project will include a system-development stage.
The Stage Plan could describe the individual products, Work Packages, resources, activities, and milestones needed during that stage.
Every PRINCE2 project has an initiation stage and at least one further stage. The initiation Stage Plan is prepared during Starting up a Project, while later Stage Plans are developed near the end of the preceding stage.
Learn more in our guide to PRINCE2 project stages and the lifecycle.
Team Plan
A Team Plan helps a Team Manager organise and control the work required to execute one or more Work Packages.
Team Plans are optional in PRINCE2.
Whether one is useful depends on the project’s complexity, delivery arrangements, and resources.
A small project might manage a straightforward Work Package without a separate Team Plan.
A larger project involving several departments, suppliers, and specialist activities may benefit from a more detailed team-level arrangement.
Exception Plan
An Exception Plan explains how a project will respond to an exception within a stage following an Exception Report and the Project Board’s decision.
For example, suppose a supplier delay threatens the agreed Stage Plan tolerance.
The Project Manager reports the forecast exception to the Project Board. If the Board decides that corrective measures should be undertaken within the stage, an Exception Plan may be prepared to describe those measures.
An Exception Plan is not automatically required whenever something goes wrong.
If the response affects work beyond the current stage, the implications must instead be addressed through an appropriate change to the Project Plan.
Exception Plans are not required for Team Plans.
Our guide to Management by Exception in PRINCE2 explains how tolerances and escalation support these decisions.
What Is Product-Based Planning in PRINCE2?
Product-Based Planning is the PRINCE2 approach to identifying what must be delivered before working out how to deliver it.
Instead of starting with the question, “What tasks should we complete?”, the project team first establishes, “What products must exist for this project to succeed?”
In PRINCE2, a product can be a tangible or intangible output that can be defined, created, and assessed.
For example, imagine a project to introduce a new employee self-service portal.
The required products might include:
- An agreed requirements specification.
- A configured employee portal.
- Migrated employee data.
- User guidance.
- A tested solution.
- A support process ready for operational use.
These products then help the team identify the activities, responsibilities, resources, and dependencies involved in creating them.
A product is what must be delivered. An activity is work undertaken to deliver it.
| Product | Related activity |
|---|---|
| Configured employee portal | Configure the portal |
| Approved requirements | Gather and agree requirements |
| Training guide | Write the training guide |
| Tested solution | Carry out system testing |
| Launch communications | Prepare and distribute launch messages |
Both products and activities are important. The distinction is that the product-focused approach helps the team avoid doing work that doesn’t contribute to the agreed outputs.
Step 1 – Define and Analyse the Products
This is the starting point of the PRINCE2 planning technique.
The aim is to establish which products must be delivered, what they must achieve, and how they relate to one another.
For the Project Plan, this includes developing the Project Product Description and then identifying and describing the required products.
Write the Project Product Description
The Project Product Description defines the overall product that the project is expected to deliver. It establishes the user’s quality expectations, acceptance criteria, and the arrangements for determining whether the completed project product is acceptable.
It identifies the user’s quality expectations and the criteria and methods that will be used to determine whether the project product is acceptable.
It is initially created during Starting up a Project and refined during Initiating a Project.
Before detailed planning begins, consider:
- What is the project intended to deliver?
- Who will use the resulting products?
- What quality expectations must be satisfied?
- What must be true for the finished project product to be accepted?
- How and by whom will acceptance be confirmed?
For our employee-portal example, a simplified project product statement might be:
Project Product: An operational employee self-service portal that allows authorised employees to access selected HR information and services.
Illustrative acceptance criteria could include successful completion of agreed functional tests, authorised access controls operating correctly, and approval by the designated business representative.
These examples would need to be refined into measurable, project-specific criteria.
The advantage of defining the Project Product early is that stakeholders can agree on what success looks like before substantial delivery work begins.
Create the Product Breakdown Structure
A Product Breakdown Structure shows the products needed within the scope of a Plan and how they are divided into components.
It helps identify the major outputs and supporting products.
For our fictional portal project, the structure might look like this:
Employee Self-Service Portal Ready for Use
- Portal solution
- Configured platform
- Access controls
- Migrated employee information
- User readiness
- Employee guidance
- Training materials
- Launch communications
- Operational readiness
- Tested solution
- Support procedures
- Support team readiness
A Product Breakdown Structure isn’t a list of activities.
For example, “migrated employee information” is a product or deliverable, while “migrate employee records” describes the work required to create it.
The structure also helps identify products that may have been overlooked.
If you’re creating one for your own project, our Product Breakdown Structure guide includes further examples and a practical checklist to help you identify and organise the required products.
Write Product Descriptions
A Product Description gives the team enough information to understand the requirements for an individual product and how its quality will be assessed.
For example, the configured employee portal might need to support specified employee functions, comply with agreed access requirements, and successfully pass particular tests.
A simplified educational Product Description could look like this:
Example Product Description
| Field | Illustrative content |
|---|---|
| Product | Employee guidance document |
| Purpose | Help employees use the new portal |
| Expected contents | Login instructions, common tasks, support information |
| Quality expectations | Clear, accurate, and accessible to intended users |
| Quality checks | HR review and sample-user testing |
| Responsible team | HR and internal communications |
This example is simplified for learning purposes. Formal Product Descriptions should contain the information required by the project’s agreed quality arrangements.
To understand how product requirements translate into measurable quality criteria and acceptance arrangements, see our PRINCE2 Quality Management guide.
The level of detail should also suit the delivery method.
For example, a linear-sequential project may need comparatively detailed Product Descriptions before scheduling and estimation.
In an iterative-incremental project, some detailed product requirements may be refined as development progresses.
Create the Product Flow Diagram
A Product Flow Diagram shows the relationships and dependencies between products.
It helps establish which products are needed before others can be developed, tested, or accepted.
For our employee-portal project, an illustrative sequence might be:
Approved requirements → Configured portal → Tested portal → Accepted solution.
However, not everything needs to happen one step after another.
Employee guidance and support procedures might be developed alongside testing, provided their necessary inputs are available.
A Product Flow Diagram should therefore represent actual dependencies, including opportunities for parallel delivery.
It can also reveal dependencies on products or activities outside the project’s control.
For example, the portal may depend on access to an external identity-management service. If that service is unavailable, the project could be affected even if its own delivery work is progressing well.
Step 2 – Organise Work Packages
Once the products and their relationships are understood, the next task is to organise the work needed to deliver them.
In PRINCE2, a Work Package provides a way of assigning defined delivery work to a Team Manager or team member.
A Work Package may contain one or more related products and the activities required to deliver them.
For our portal example, the project might have separate Work Packages for platform configuration, employee guidance, and operational support preparation.
The Work Package Description explains the work being authorised, the products involved, constraints, responsibilities, reporting requirements, and relevant targets and tolerances.
This supports clear accountability: the Project Manager manages the authorised work, while the responsible delivery team understands what it must produce.
A Work Breakdown Structure can help organise the activities associated with Work Packages.
The Project Manager should also ensure that Work Packages collectively cover the delivery scope without unnecessary overlap or gaps.
Step 3 – Prepare Estimates
Estimating establishes the people, resources, time, costs, and other quantities needed to deliver the planned work.
PRINCE2 planning considers estimates relating to areas such as:
- People and specialist skills.
- Materials, equipment, facilities, and other resources.
- Activity durations.
- Labour and resource costs.
- Expected benefits.
- Risks and potential responses.
An estimate is not a guarantee.
For example, a team may initially estimate that configuring the employee portal will require ten working days.
However, that estimate may depend on requirements being agreed, the technical team being available, and the necessary systems being accessible.
Recording these assumptions makes it easier to understand and challenge the estimate.
Confidence in estimates also matters.
Where work is unfamiliar or technically uncertain, the team may need to refine its estimates as more information becomes available.
This is one reason detailed Stage Plans are useful: they allow shorter-term work to be planned using better information.
Step 4 – Prepare the Schedule
The schedule translates the proposed work into a time-based delivery arrangement.
It draws on the products, Work Packages, dependencies, activity durations, and available resources identified during planning.
A useful schedule should show:
- The work that must be completed.
- The sequence of activities.
- Important dependencies.
- Estimated durations.
- Relevant resource allocations.
- Key delivery milestones.
For example, testing the portal cannot be completed before a suitable version of the portal exists.
However, preparing staff communications may be possible while technical testing continues.
By understanding these relationships, the Project Manager can develop a more realistic schedule.
The schedule can be represented using different tools, including a Gantt chart, spreadsheet, product checklist, or activity flow board.
Remember: the schedule forms part of the Plan. It is not the entire Plan.
Step 5 – Prepare the Budget
Once the work, people, resources, and scheduling requirements are better understood, the project team can prepare the budget.
This should account for the expected costs of producing and delivering the products, together with the management activities needed to run the project.
Depending on the project, these costs may include:
- Internal or external labour.
- Specialist suppliers.
- Software or equipment.
- Materials and facilities.
- Testing and implementation.
- Project management activities.
- Appropriate allowances for risk and change.
PRINCE2 recognises risk and change budgets, although maintaining these as separate budgets is optional and should be appropriate to the project’s circumstances.
For the portal example, the budget might include platform configuration, supplier services, employee training, and testing.
The key is to connect costs with the planned work rather than developing a budget independently of delivery requirements.
Step 6 – Analyse Risks
Risk analysis is an ongoing part of PRINCE2 planning, not simply a final step after the schedule and budget have been prepared.
As the Plan develops, the project team considers uncertainties that may affect its delivery.
For the employee-portal project, potential risks might include:
- Delays in obtaining access to existing systems.
- Unavailable technical specialists.
- Poor-quality source data.
- Additional integration requirements.
- Employees needing more support than anticipated.
For each relevant risk, consider how it might affect the proposed activities, resources, costs, schedule, or achievement of the project’s objectives.
For example, concerns about data quality could lead the project team to plan additional verification before migration.
Risks should be recorded and managed using the project’s agreed risk management arrangements.
The proposed Plan may need to change after risk responses have been considered.
This means that good planning is not simply about identifying the fastest route to delivery. It involves developing a realistic approach that takes uncertainty into account.
For a deeper explanation, see our article on PRINCE2 Risk Management.
Step 7 – Document the Plan
The final part of the technique brings the planning information together so that it can be reviewed, understood, approved, and used.
A documented PRINCE2 Plan may draw on several different sources, including spreadsheets, schedules, diagrams, and management information systems.
An accompanying summary can help explain:
- The Plan’s scope and purpose.
- Major products and Work Packages.
- Important dependencies.
- Planning assumptions.
- Budgets and schedules.
- Key risks.
- Proposed tolerances.
- Monitoring and reporting arrangements.
For a Project Plan, the information should also describe the management stages and planned Project Board decision points.
Once the appropriate Plan has been reviewed and approved, it provides a baseline for monitoring and control.
The Project Plan is approved by the Project Board, and the relevant arrangements for approval and control should follow the project’s agreed PRINCE2 responsibilities.
How Do Tolerances Affect the Project Plan?
PRINCE2 uses tolerances to define how far performance may vary from agreed targets before escalation is necessary.
The method recognises seven performance aspects: benefits, cost, time, quality, scope, sustainability, and risk.
However, the tolerances used at different management levels must be appropriate to the relevant Plan and the responsibilities being delegated.
For example, a Stage Plan may specify the permissible variation in its completion date or cost.
If the Project Manager forecasts that an agreed stage tolerance will be exceeded, the matter must be escalated appropriately.
This allows management decisions to be made at the right level without requiring senior management to approve every minor adjustment.
The approach is known as Management by Exception.
PRINCE2 Project Plan Example
Let’s bring the planning technique together using a fictional example.
Imagine an organisation wants to introduce an employee self-service portal to reduce routine HR administration and make selected employee information easier to access.
The organisation has approved the idea, but it now needs a workable Project Plan.
Define the End Product
Project Product: An employee self-service portal configured, tested, accepted, and ready for operational use.
The project team agrees the major user requirements and identifies who will accept the finished solution.
The intended benefits might include reducing manual administrative work and improving access to HR services. These would need to be defined and measured appropriately through the project’s Business Case and benefits management arrangements.
Identify the Required Products
The team identifies the main outputs:
| Product | Purpose |
|---|---|
| Approved requirements | Define the agreed capabilities |
| Configured portal | Provide the required functionality |
| Prepared employee data | Support the agreed portal services |
| Tested solution | Demonstrate compliance with quality requirements |
| Employee guidance | Help people use the portal |
| Operational support arrangements | Prepare the organisation to support users |
These products form the basis of the Product Breakdown Structure and Product Descriptions.
Identify Dependencies
The team then establishes how the products relate.
For example, portal configuration depends on approved requirements, while formal acceptance depends on successful testing.
Employee guidance may be developed in parallel with configuration, but final instructions should reflect the solution employees will actually use.
This information helps the team sequence delivery without assuming every product must be developed consecutively.
Organise Work Packages and Prepare Estimates
The Project Manager groups related work into suitable Work Packages.
For illustration, the project might use:
| Work Package | Example activities | Primary resource |
|---|---|---|
| Portal configuration | Configure services and access | Technical team |
| Data preparation | Review and prepare data | HR and data specialists |
| Testing | Execute and record tests | Technical and user representatives |
| Employee readiness | Create guidance and prepare training | HR and communications |
The team then estimates how much effort, time, and funding each Work Package will require.
Prepare a Schedule and Budget
An illustrative high-level schedule could be:
| Period | Main focus |
|---|---|
| Weeks 1–2 | Confirm detailed requirements and delivery arrangements |
| Weeks 3–5 | Configure the portal and prepare data |
| Weeks 6–7 | Test the solution and prepare employee guidance |
| Week 8 | Complete acceptance activities and operational handover |
These timings are fictional educational estimates, not standard PRINCE2 durations.
Actual scheduling would need to account for dependencies, resource availability, risks, and the organisation’s delivery arrangements. Some of the work may run in parallel.
The budget would then be developed using the estimated people, resource, supplier, and management costs.
Analyse Risks and Establish Controls
The team identifies important uncertainties, such as incomplete employee data or delayed technical integration.
It also determines how progress will be monitored, when reporting is required, and which decisions must be escalated.
Appropriate targets and tolerances are agreed through the relevant project management levels.
The completed Project Plan provides an overall picture of delivery, while Stage Plans provide greater detail for the work being managed in each stage.
This is the real value of the PRINCE2 planning technique: it connects what needs to be delivered with how delivery will be organised and controlled.
Free PRINCE2 Project Planning Template
You don’t need to start with a blank document.
Our proposed PRINCE2 Project Planning Toolkit is designed to help you apply the concepts in this guide to your own project.
The toolkit contains two original, editable learning resources informed by the current PRINCE2 Plans Practice: a Word Project Plan Template and an Excel Project Planning Workbook. Both are designed to help you put the planning technique into practice.
What Does the Toolkit Include?
Word Project Plan Template
A structured document for recording the project’s purpose, scope, products, dependencies, assumptions, management stages, budgets, risks, and controls.
Excel Project Planning Workbook
An editable workbook for organising product information, Work Packages, estimates, resources, schedules, costs, risks, and monitoring arrangements.
The two formats complement one another. Word helps explain and document the proposed Plan, while Excel makes it easier to organise the supporting planning information.
How Should You Use the Template?
Begin by describing the overall project and the products it needs to deliver.
Next, build the Product Breakdown Structure and identify dependencies.
Then develop your Work Packages, estimates, schedule, and budget.
Use the risk and control sections to record the assumptions and arrangements that affect delivery.
Finally, adapt the template to your project’s scale, delivery method, organisational requirements, and agreed management approach.
Important: This is an original ITonlinelearning learning resource, not an official PeopleCert/PRINCE2 management-product template.
Do You Need a Gantt Chart for a PRINCE2 Project Plan?
No. PRINCE2 does not require every Project Plan to use a Gantt chart.
A Gantt chart is one possible way to present the schedule, but current PRINCE2 guidance also recognises other scheduling and presentation approaches.
A spreadsheet may be suitable for a relatively simple project. An activity flow board may be more appropriate for teams using iterative-incremental delivery.
The choice depends on how the project is managed and what information people need.
The important distinction is that a Gantt chart presents scheduling information. It doesn’t replace the wider planning information needed to manage the project.
Does PRINCE2 Require the Whole Project to Be Planned Upfront?
No. PRINCE2 uses planning horizons and management stages so that detail can be developed when reliable information becomes available.
A Project Plan provides the overall direction for the project.
Stage Plans provide more detailed information for the work about to be undertaken.
This allows the Project Manager to use experience from earlier stages to improve estimates and delivery arrangements for later stages.
For example, a Project Plan might identify the major products and expected delivery periods for a year-long technology project.
The Stage Plan for the next two months could describe particular Work Packages, people, resources, and activities in much greater detail.
This doesn’t mean the project has no long-term Plan. It means different levels of detail are used for different decisions.
Can a PRINCE2 Project Plan Be Agile?
Yes. Current PRINCE2 supports linear-sequential, iterative-incremental, and hybrid delivery approaches.
PRINCE2 provides a management framework within which the project can select suitable ways of developing its products.
For example, a digital project could use PRINCE2 to establish its overall Business Case, Project Plan, stages, responsibilities, and control arrangements.
Its development team might use iterative delivery to build and refine software through short cycles.
In that situation, a product backlog or team workflow board may be more useful for managing detailed development activities than a conventional fixed schedule.
The project’s higher-level management arrangements and detailed delivery arrangements should remain aligned.
This flexibility is one reason the statement that PRINCE2 is automatically Waterfall is misleading.
For more information, read Is PRINCE2 Waterfall? or our PRINCE2 vs Agile comparison.
How Detailed Should Your PRINCE2 Project Plan Be?
A PRINCE2 Project Plan should contain enough information to support the decisions, communication, and controls required for the project.
It shouldn’t contain detail merely for the sake of documentation.
A relatively straightforward internal project may need a compact Plan with a small number of products, Work Packages, and management stages.
A complex project involving multiple suppliers, important regulatory requirements, or significant uncertainty will usually require more extensive planning information.
Consider:
- The scale and complexity of the work.
- The delivery approach.
- The level of risk.
- The planning horizon.
- The number of teams and suppliers.
- The decisions that need to be made.
- The organisation’s reporting and assurance requirements.
The aim is to use enough planning detail to manage the project effectively without creating unnecessary work.
You can explore this further in our guide to tailoring PRINCE2 to different projects.
Common Mistakes When Creating a PRINCE2 Project Plan
Even a detailed Plan may be difficult to use if its foundations are unclear.
Some common mistakes to avoid include:
- Starting with activities rather than products. Agree what must be delivered before deciding what work is needed.
- Treating the schedule as the whole Plan. Include the wider information necessary to understand and control delivery.
- Leaving quality requirements unclear. Product Descriptions and acceptance criteria should explain what successful delivery means.
- Overlooking dependencies. A missing external dependency can undermine an otherwise realistic schedule.
- Estimating without considering resources. An activity’s duration is affected by the people, skills, and resources available.
- Treating risk analysis as a final formality. Reconsider risks throughout the development of the Plan.
- Planning future stages in excessive detail. Use appropriate planning horizons and refine shorter-term work as better information becomes available.
- Using the same planning template for every project. Tailor the format, level of detail, and controls to suit the project context.
- Introducing unapproved work into Stage Plans. Detailed activities should remain traceable to the approved higher-level scope.
- Failing to maintain the Plan. Review and update planning information when necessary so it continues to support decisions and control.
PRINCE2 Project Plan Checklist
Before submitting your Plan for approval, check that you can answer the following questions.
- Have we defined the project’s major products and intended outcomes?
- Are the relevant quality requirements and acceptance arrangements understood?
- Have we identified the products that must be delivered?
- Are important product dependencies clear?
- Have the required Work Packages been defined?
- Do we have realistic estimates of people, resources, duration, and costs?
- Does the schedule reflect dependencies and resource availability?
- Have we prepared an appropriate budget?
- Have risks been identified and considered throughout planning?
- Are the planning assumptions and prerequisites recorded?
- Are the management stages and decision points appropriate?
- Have suitable performance targets, tolerances, and controls been established?
- Are the monitoring and reporting arrangements clear?
- Is the level of detail appropriate for the project?
- Has the Plan been reviewed by the relevant people?
This checklist is an educational aid rather than an official PRINCE2 assessment of compliance.
Frequently Asked Questions About PRINCE2 Project Planning
What Should a PRINCE2 Project Plan Contain?
A PRINCE2 Project Plan should provide the information needed to understand and control overall project delivery. This includes the project’s scope, products, Work Packages, dependencies, assumptions, budget, schedule, relevant targets and tolerances, and monitoring arrangements. It should also identify the management stages and important Project Board decision points. The exact presentation can be tailored to the project.
What Is the Difference Between a Project Plan and a Stage Plan?
The Project Plan provides an overall view of the project lifecycle, while a Stage Plan describes the detailed work to be managed within a particular stage. Stage Plans normally include more detail because they cover a shorter planning horizon. Both should remain aligned so that detailed delivery work contributes to the approved project objectives.
What Is a Product Breakdown Structure in PRINCE2?
A Product Breakdown Structure is a hierarchy of the products required within the scope of a Plan. It breaks major products into their component products so that the project team can identify what needs to be delivered. It focuses on outputs rather than listing the activities required to create them.
What Is a Product Flow Diagram?
A Product Flow Diagram shows the relationships and dependencies between products. It helps the project team understand the order in which products need to be developed and which outputs can be progressed in parallel. This information supports the later identification of delivery activities, Work Packages, and scheduling requirements.
What Is the Difference Between a Project Product Description and a Product Description?
A Project Product Description defines the project’s major products or intended outcomes and includes the user’s quality expectations and overall acceptance arrangements. An individual Product Description provides more detailed information about a particular product and its requirements. Together, they support clarity about what needs to be delivered and how its quality will be assessed.
Is a Team Plan Mandatory in PRINCE2?
No. Team Plans are optional in PRINCE2. They may be used when a Team Manager needs a separate Plan to organise and control delivery of one or more Work Packages. Their usefulness depends on the project’s complexity, resources, and delivery arrangements.
When Is an Exception Plan Needed?
An Exception Plan may be prepared following an Exception Report when the Project Board directs action to address a project or stage exception within the stage. It explains how the required response will be carried out. Not every issue or forecast breach automatically results in an Exception Plan, and Exception Plans are not required for Team Plans.
Can You Use Excel to Create a PRINCE2 Project Plan?
Yes. Excel can be used to organise and maintain project planning information, including products, activities, estimates, schedules, and budgets. However, a spreadsheet must still provide or connect to the information needed for the wider Plan. PRINCE2 does not require a particular software application for documenting planning information.
Does PRINCE2 Use Progressive Planning?
Yes. PRINCE2 uses planning horizons and Stage Plans to develop more detailed delivery arrangements closer to when work will take place. The Project Plan establishes overall direction, while subsequent Stage Plans can incorporate lessons, updated estimates, and changing circumstances. This approach avoids relying on unnecessarily detailed long-term estimates where uncertainty is high.
Is There an Official PRINCE2 Project Plan Template?
PeopleCert’s official PRINCE2 guidance includes management-product outlines and information about Plans. Separately, training providers and organisations may create their own educational planning resources. ITonlinelearning’s downloadable toolkit is an original learning resource informed by current PRINCE2 concepts; it is not an official PeopleCert template.
Can You Use PRINCE2 Planning for Agile Projects?
Yes. PRINCE2 can be used with iterative-incremental and hybrid delivery methods. The management framework establishes the project’s direction, responsibilities, stages, and controls, while delivery teams can use suitable adaptive planning approaches. The level of product detail and scheduling can be tailored to the needs of the project.
What Should You Explore Next?
Creating a PRINCE2 Project Plan is about much more than listing activities and allocating deadlines.
The key is to start with the products the project must deliver and then establish the work, resources, timing, budget, and controls needed to achieve them.
If you understand this relationship, you’ll be better equipped to create plans that help people make decisions rather than simply document their intentions.
To put the process into practice, use the original ITonlinelearning planning toolkit alongside the worked example in this guide.